The Delhi High Court on Friday issued notice to the CBI in an appeal moved by Gautam Kumar Basak, former Executive Secretary, Joint Plant Committee in the Union Steel Ministry challenging his conviction and 3-years jail term by a trial Court in a case of corruption in coal block allocation.
The bench of Justice Amit Sharma while seeking a response from the CBI, also suspended Basak’s sentence till December 15 this year.
Advocate Ajeet Singh appeared for the appellant Gautam Kumar Basak in the matter in the Delhi High Court.
On August 22 this year, a trial court awarded 3 years of rigorous imprisonment and imposed a fine of Rs 5 lakh upon Basak. The trial court also acquitted Soumen Chaterjee co-accused in the matter.
Special Judge Arun Bhardwaj convicted Gautam Kumar Basak under Section- 13(2) read with Section 13 (1)(d) of the Prevention of Corruption Act 1988.
According to CBI, The Union Ministry of Coal (MOC) in November 2006 invited applications from the companies engaged in generation of power, steel and cement for allocation of coal blocks for captive power plants/independent power plants.
In response to the advertisement issued by MOC, number of companies applied for coal blocks. Prakash Industries Ltd. applied for Vijay Central Coal Block situated in Chhattisgarh. Earlier, Chotia Coal Block was allocated to Prakash Industries Ltd, stated CBI.
Furthermore, CBI added that in the application dated January 12, 2007 submitted to Unnion Coal Ministry, Prakash Industries Ltd. claimed its sponge iron production capacity as 8 MTPA.
Believing the claim made by Prakash Industries Ltd, the Screening Committee of the Ministry of Coal recommended joint allocation of Vijay Central Coal Block in favour of Prakash Industries Ltd. and SKS ISpat Ltd. & Ors.
These recommendations were sent to the Prime Minister’s Office for final approval. In the meantime complaints were lodged by SKS Ispat Ltd, Youth Anti-Corruption Bureau, and Om Prakash, Member of Parliament, Lok Sabha, Samajwadi Party alleging that Prakash Industries Ltd. has secured recommendation of the Screening Committee by furnishing false information about its capacity.
However, in the view of these complaints, the Coal Ministry directed the Steel Ministry to verify claims made by Prakash Industries Ltd. in its application.
Accordingly, the Ministry of Steel directed Gautam Kumar Basak to conduct on the spot verification of the plant of Prakash Industries Ltd. at Champa, Raipur Chhattisgarh.
On August 4, 2008, Basak along with Soumen Chatterjee Manager, JPC allegedly visited the plant of M/s Prakash Industries Ltd., at Champa, Raipur Chhattisgarh and on August 5, 2008 submitted a false report supporting the claims of Prakash Industries Ltd and mentioning that Prakash Industries Ltd, has 4 kilns and its sponge iron production capacity is 8 MTPA.
CBI stated that, this false report submitted by Basak was forwarded by the Ministry of Steel to the Ministry of Coal and the Prime Minister’s Office.
Again, SKS Ispat Ltd and Youth Anti-Corruption Bureau lodged complaints with the Ministry of Steel & Ministry of Coal.
Ultimately one Inter-Ministerial committee was constituted by the Centre to find out the truth. This Inter-Ministerial committee conducted on the spot verification and concluded that Prakash Industries Ltd, had furnished false information about its capacity in its application and Basak submitted false verification report to support the claims made by Prakash Industries Ltd.
FIR was registered in this matter by CBI on April 7, 2010.
The Punjab and Haryana High Court on Tuesday has issued a notice to Jindal Global…
The ED on Tuesday has filed a Prosecution Complaint before the Special Court in Mohali…
The Supreme Court on Tuesday denied bail to Arunkumar Devnath Singh, whose son is a…
The Supreme Court on Tuesday dismissed the Centre's appeal against a Bombay High Court order…
The Supreme Court on Tuesday has agreed to review a plea from retired Army Captain…
The Chhattisgarh Anti-Corruption Bureau on Tuesday has registered a case against 2 retired IAS officers…